Tanker approaches to the factory
backwardly. First process begins after milk pump is connected to
the tank. Filtered milk is sent to milk boiler. Milk which is
boiled up to 30 degrees is transferred to the separator machine.
After this process, milk is transferred to milk vacuum machine
by boiling up to 90-92 C . Then, milk transferred to resting
bowl. Milk is cooled down to 60 C. 200, 500, 800, 1100, 1250,
1500, 2000, 2750, 3000, 3500, 4000, 5000, 10000 and 18000 gr.
yoghurt cases are placed on approximately 30 stainless
carriages. Milk is poured to these cases by pump gun.
So
far, elapsed time is between 05:00-11:00. Yoghurt carriages go
through the final control after fulfilling. Yeasted yoghurt is
started to be heated. When the room temperature is 60 C and
yoghurt temperature is 50 C, heating process stops and yoghurt
is rested. After the temperature decreases to 40-45 C, yeast is
made from our natural yoghurt. Yoghurt is yeasted by yeast gun.
Since yoghurt temperature decreases to 40 C during yeasting
process, temperature is increased to 50 C and yeasting process
is ended. Milk starts to transform yoghurt, and room temperature
is decreased by a ventilator cooling system. Between 11:00-15:00
yoghurt is rested. Milk finally transforms yoghurt. Yoghurts are
transferred to the ice room and rested until next morning.
Then, dairy products are transported to the mass consumption and
sales locations via 5 company vehicles nearly 06:00. Remaining
5-6 tons products are given to merchants according to bonus
system. This sale process begins from 06:00 to 14:00. |